Project Overview | |
Power Station: | Huaqiang TeraSolar 15MW Fresnel |
Location: | Zhangbei, Zhangjiakou, Zhangjiakou |
Owners (%): | Zhangbei Huaqiang Zhaoyang Co., Ltd. (Xinli Energy Development Co., Ltd.) |
Technology | Linear Fresnel |
Solar Resource: | 1767 |
Nominal Capacity: | 15 MW |
Status | Operational |
Start Year: | 2018 |
Status Date | October 25, 2023 |
Background | |
Break Ground Date | 2015 |
Expected Generation (GWh/year) | 75 |
Lat/Long Location | 41.214,114.573 |
Participants | |
Developer | Shenzhen Huaqiang Zhaoyang Energy (Xinli Energy Development Co., Ltd.), China |
EPC | TeraSolar, Xian New Energy |
Costs | |
Total Construction Cost (2018) | 700.00 million |
Total Cost USD (2020) | $105.49 million |
Specific Cost/kW USD (2020) | 7033 |
LCOE USD/kWh (2020) | 0.12 |
Levelised cost of electricity with 5% weighted average cost of capital and a 25 year payback period, capacity dependent O&M (1.5% of investment cost per year), deflated from Year_operational using the Worldbank’s GDP deflator; if station under development or construction then not deflated (assumed cost year 2020) | |
Remuneration Start Year | 2018 |
Plant Configuration | |
Solar Field | |
Solar Field Aperture Area (m2) | 170000 |
Collector/Heliostat Engineering or IP Owner | TeraSolar, China |
Collector/Heliostat Model | HLIACS |
Solar Field (Receiver) | |
Receiver Working Fluid | Water |
Receiver Working Fluid Category | Water |
Working Fluid Manufacturer | TeraSolar |
Receiver Manufacturer | TeraSolar |
Power Block | |
Nominal Turbine or Power Cycle Capacity | 15 MW |
Power Cycle | Steam Rankine |
Thermal Energy Storage | |
Storage Type | Other |
Storage Capacity (Hours) | 14 |
Storage Description | Solid state formulated concrete |
TES Engineering Company | TeraSolar China |