Project Overview | |
Power Station: | CEIC Dunhuang 100MW Fresnel + 600MW PV |
Location: | Dunhuang, Jiuquan, Gansu, China |
Technology | PV-Hybrid, Fresnel |
Solar Resource: | 1649 |
Nominal Capacity: | 100 MW |
Status | Under Construction |
Start Year: | 2024 |
Status Date | October 25, 2023 |
Background | |
Break Ground Date | 2021 |
Total Power Station Land Area (km2) | 14.3 |
Participants | |
Developer | China Energy Group Longyuan Power Gansu Company, China |
Electricity Generation Offtaker | Gansu State Grid Electric Power |
Costs | |
Remuneration RMB/kWh | 0.31 |
Remuneration Start Year | 2021 |
Remuneration USD/kWh Deflated (2020) | 0.05 |
Support Scheme Type | FIT |
Policy Support Scheme | Subsidy free, supported by provincial coal tariff. |
Plant Configuration | |
Solar Field | |
Collector/Heliostat Engineering or IP Owner | Lanzhou Dacheng, China |
Solar Field (Receiver) | |
Receiver Working Fluid | Molten Salt |
Receiver Working Fluid Category | Salt |
Receiver Manufacturer | Lanzhou Dacheng Vacuum Technology Co. (Lanzhou Dacheng Technology Co., Ltd), China |
Power Block | |
Nominal Turbine or Power Cycle Capacity | 100 MW |
Thermal Energy Storage | |
Storage Description | Molten Salt |
China: Yumen Xinneng/Xinchen 50MW Beam-down CSP
Project Overview Power Station:Yumen Xinneng / Xinchen - 50MW Beam-downLocation:YumenJiuquanGansu ChinaOwners (%):Yumen Xinneng Thermal Power Co., Ltd owned by Thvom...