The plant, constructed by a consortium led by ACCIONA for the company EIG Global Energy Partners, has a 110 MW capacity and is the first of its type constructed in Latin America.
Project Overview | |
Power Station: | Atacama I / Cerro Dominador 110MW CSP + 100MW PV |
Location: | Calama, Antofagasta, Chile |
Owners (%): | EIG |
Technology | Power Tower |
Solar Resource: | 3186 |
Nominal Capacity: | 110 MW |
Status | Operational |
Start Year: | 2021 |
Status Date | October 25, 2023 |
Background | |
Break Ground Date | 2018 |
Lat/Long Location | -22.771,-69.479 |
Total Power Station Land Area (km²) | 7 |
Participants | |
Developer | Abengoa, Spain |
EPC | Abengoa, Acciona |
Operator | Abengoa Solar |
Electricity Generation Offtaker | Sistema Interconectado del Norte Grande (SING) |
Costs | |
Total Construction Cost (2017) | $ 1400.00 million |
Support Scheme Type | PPA |
Concessional Funding or Other Support | Inter-American development bank, World bank CTF, KfW (100 million €), EU (15 million €) |
Plant Configuration | |
Solar Field | |
Solar Field Aperture Area (m²) | 1484000 |
# of Heliostats (or dishes for dish systems) | 10600 |
Heliostat Aperture Area (m²) (or dish aperature for dish systems) | 140 |
Collector/Heliostat Manufacturer | Abengoa, Spain |
Collector/Heliostat Engineering or IP Owner | Abengoa, Spain |
Collector/Heliostat Model | ASUP 40V3 |
Mirror Manufacturer | Rioglass, Spain |
Solar Field (Receiver) | |
Receiver Working Fluid | Molten Salt |
Receiver Working Fluid Category | Salt |
Tower Height (m) | 252 |
Receiver Manufacturer | Cockerill, Belgium |
Power Block | |
Nominal Turbine or Power Cycle Capacity | 110 MW |
Turbine Manufacturer | Doosan Skoda Power, Czechia |
Power Cycle | Steam Rankine |
Cooling Type | Dry |
Thermal Energy Storage | |
Storage Type | 2-tank direct |
Storage Capacity (Hours) | 17.5 |
Storage Description | Molten salt |
Cerro Dominador project is a 210MW hybrid concentrated solar power (CSP) and photovoltaic (PV) power complex under construction on a 1,000ha-site, approximately 60km away from Calama at Maria Elena in the Atacama Desert, Chile.
Construction on the $1.4bn project, which consists of a 100MW PV plant and 110MW CSP plant, was started in 2014.
The PV plant was commissioned in February 2018, while the Cerro Dominador CSP plant, the first solar thermal power project in Latin America, is expected to commence operation by the end of 2019.