Project Overview | |
Power Station: | SIDC Ruoqiang 100MW Tower + 900MW PV |
Location: | Ruoqiang |
Bayingolin | |
Xinjiang (XUAR) China | |
Technology | PV-Hybrid, Tower |
Solar Resource: | 1767 |
Nominal Capacity: | 100 MW |
Status | Under Construction |
Start Year: | 2025 |
Background | |
Break Ground Date | 2023 |
Expected Generation (GWh/year) | 150.6 |
Participants | |
Developer | State Development and Investment Corporation (SDIC) |
China | |
EPC | North China Electric Power Design Institute (NCEPDI) of CEEC, Shouhang Hi-Tech |
China | |
Construction Job Years | 2000 |
Costs | |
Total Construction Cost (2022) | 1690.00 million |
Total Cost USD (2020) | $251.3 million |
Specific Cost/kW USD (2020) | 2513 |
LCOE USD/kWh (2020) | 12 |
Levelised cost of electricity with 5% weighted average cost of capital and a 25 year payback period, capacity dependent O&M (1.5% of investment cost per year), deflated from Year_operational using the Worldbank’s GDP deflator; if station under development or construction then not deflated (assumed cost year 2020) | |
Policy Support Scheme | Subsidy free, supported by provincial coal tariff. |
Plant Configuration | |
Solar Field | |
Collector/Heliostat Engineering or IP Owner | Shouhang |
China | |
Solar Field (Receiver) | |
Receiver Working Fluid | Molten Salt |
Receiver Working Fluid Category | Salt |
Power Block | |
Nominal Turbine or Power Cycle Capacity | 100 MW |
Turbine Manufacturer | Dongfang |
China | |
Thermal Energy Storage | |
Storage Capacity (Hours) | 8 |
Storage Description | Molten Salt |
China: Yumen Xinneng/Xinchen 50MW Beam-down CSP