Project Overview | |
Power Station: | Augustin Fresnel 1 |
Location: | Targassonne, Occitanie, France |
Owners (%): | Solar Euromed |
Technology | Linear Fresnel |
Solar Resource: | 1800 |
Nominal Capacity: | 0.3 MW |
Status | Operational |
Start Year: | 2012 |
Status Date | October 21, 2022 |
Background | |
Break Ground Date | 2011 |
Lat/Long Location | 42.501,1.972 |
Total Power Station Land Area (km2) | 0.01 |
Participants | |
Developer | Solar Euromed, France |
EPC | Solar Euromed |
Operator | Solar Euromed |
Construction Job Years | 10 |
Annual Operations Jobs | 3 |
Costs | |
Concessional Funding or Other Support | French Goverment Co-funding |
Plant Configuration | |
Solar Field | |
Solar Field Aperture Area (m2) | 400 |
# of Lines | 1 |
Mirror Line Length (m) | 40 |
Mirror Manufacturer | Solar Euromed |
France | |
Solar Field (Receiver) | |
Receiver Working Fluid | Water |
Receiver Working Fluid Category | Water |
Solar Field or Receiver Outlet Temperture (C) | 300°C |
Receiver Manufacturer | Solar Euromed, France |
Receiver Model | AF1 |
Power Block | |
Nominal Turbine or Power Cycle Capacity | 0.3 MW |
Power Cycle | Steam Rankine |
Power Cycle Pressure (Bar) | 100 |
Cooling Type | Dry |
Thermal Energy Storage | |
Storage Type | Other |
Storage Capacity (Hours) | 0.25 |
Storage Description | Ruths tank |
China: Yumen Xinneng/Xinchen 50MW Beam-down CSP