Project Overview | |
Power Station: | Stillwater GeoSolar Hybrid Plant |
Location: | Fallon |
Nevada United States | |
Owners (%): | ENEL |
Technology | Parabolic Trough |
Nominal Capacity: | 2 MW |
Status | Operational |
Start Year: | 2015 |
Status Date | December 05, 2021 |
Background | |
Break Ground Date | 2014 |
Expected Generation (GWh/year) | 3 |
Lat/Long Location | 39.548,-118.556 |
Total Power Station Land Area (km2) | 0.08 |
Participants | |
Developer | ENEL |
Italy | |
EPC | SkyFuel |
Operator | Enel |
Electricity Generation Offtaker | NV Energy |
Costs | |
PPA or Tariff Period (Years) | 20 |
Plant Configuration | |
Solar Field | |
# of Modules per SCA | 8 |
SCA Aperture Area (m2) | 656 |
SCA Length (m) | 115 |
Collector/Heliostat Engineering or IP Owner | SkyFuel |
USA | |
Collector/Heliostat Model | SkyTrough |
Mirror Manufacturer | ReflecTech |
USA | |
Solar Field (Receiver) | |
Receiver Working Fluid | Water |
Receiver Working Fluid Category | Water |
Power Block | |
Nominal Turbine or Power Cycle Capacity | 2 MW |
Power Cycle | Organic Rankine |